When we were approached in June 2023, Barratt Homes had already commissioned a formal design. Normally we have full cycle involvement but, on this occasion, we were invited to tender by M & J Evans, the groundworker.
There was a short lead in time on this project. Using our industry connections, we were able to get on site quickly making sure we had enough materials to meet the start date of 6th September. The remainder of the materials were then supplied in good time and the walls were substantially complete by 27th October.
Prior to our involvement Barratt Homes had employed GRM Development Solutions Ltd. to provide a 3rd party inspection of the walls. Their principal geotechnical engineer visited the site and confirmed that the wall, geogrid, compacted stone layers, grid lengths, drainage pipes and sleeves for the wall were all built in accordance with the design.